Project Schedule
Construction of the Arts and Transit Project began in 2013 and was completed in fall 2017. Construction milestones for the project include:
Early Spring 2013 | Demolition and site mobilization | |
Summer 2013 | Construction of new commuter parking lot and temporary train platform; Alexander Street utility relocation | |
Fall 2013 | New commuter parking lot and temporary train platform open; renovation of existing station buildings begins | |
Fall 2013-Early 2014 | Construction of Alexander Street-University Place roundabout | |
Fall 2014 | New train station, Wawa and transit plaza open; access road from Alexander Street to West Garage (Lot 7) opens | |
Fall 2017 | Arts buildings open |