Wu and Wilcox Halls

Project Description
This project will create a new combined servery for Butler and Wilson Colleges. Dining room improvements and a new kitchen are also planned. A new entry addition on Goheen Walk will give Wilcox hall a new look while providing a new stair and passenger elevator. This new elevator, as well as new ramps, will provide barrier-free access to all floors. Barrier-free toilet rooms will also be provided on the second floor. Life safety improvements include upgraded fire alarm systems and extended fire suppression systems. Much of the aging building infrastructure will also be replaced or improved as part of this project with new energy-efficient systems.
Estimated Completion
Project phases will be delivered in fall of 2007, 2008 and 2009.
Area
46,200 GSF
Project Update

Progress as of February 18, 2009. See additional progress frames in the photo gallery.
Photo Gallery
Renderings and construction photos are located in the photo gallery. Please note that renderings and artists' conceptions are presented here for historical purposes only. The final designs of these projects may have evolved since these renderings were created
Construction Team
| Design Architects | Michael Graves and Associates |
| Construction Manager | HSC Builders and Construction Managers |
Princeton Representation
| Program Manager | Jay Belli |
| Project Manager | N. Ann Walker |