Community Information
Andlinger Laboratory Construction
Project Milestones
- Start Excavation – April 2012
- Start Structural Steel – October 2012
- Complete Foundations – December 2012
- Start Tower Construction – February 2013
- Complete Superstructure – June 2013
- Complete Exterior Envelope – May 2014
- Cleanroom Protocol Level 4 Achieved – September 2014
- Construction Complete – March 2015
Pedestrian Pathways
For safety reasons, there are no pathways through the construction site. Please use the pathways around the site indicated by the arrows on the construction map.

Excavation
Excavation will begin in April 2012 using a surface excavator technology. We are not currently planning to utilize any controlled blasting at the site during excavation.